Project Package 

Baseline Project Plan:

The proposed key milestone dates: 

  • Publish Phase 1 Initial Report for Public Comment - 21 April 2023
  • Submit Phase 1 Final Report to the GNSO Council - 03 November 2023
  • Publish Phase 2 Initial Report for Public Comment - 25 April 2025
  • Submit Phase 2 Final Report to the GNSO Council - 07 November 2025
    • Note: since the EPDP Team is not expected to start Phase 2 deliberation before November 2023, the projected milestone dates for Phase 2 have more uncertainty and are subject to change, based on the observation of the team’s progress during Phase 2 deliberations.